Key Highlights
- The project involves the establishment of a 400/220 kV Velgaon GIS substation along with LILO of 400 kV and 220 kV transmission lines and associated works.
- The implementation period is 24 months.
- On the same day, Jejuri Hinjewadi Power Transmission Limited was handed over to The Tata Power Company Limited.
- The scheme envisages the construction of an approximately 115 km long 400 kV double-circuit transmission line from Jejuri to Hinjewadi, along with associated works, to be completed within 24 months.
- The successful handover of these SPVs highlights RECPDCL’s continued role as a leading bid process coordinator, strengthening Maharashtra’s transmission infrastructure through transparent and competitive bidding.